Project Description:  This project consists of This project consisted of the construction document revisions to the new distribution EV charging station distribution system and removing the Neutral to Grounding Electrode bond at the existing main disconnecting means.

Project Scope of Work:  

This project included providing stamped electrical engineered drawings indicating new exterior switchgear, updating the existing building service, providing EV bus charging stations within the exiting 20,000 Square foot transportation facility.

We also provided provisions for future Solar PV system and Future Exterior EV Car charging dispensers. All scope of work was modeled in Revit 3D and final installation was 3D scanned to confirm accurate installation and final scope was indicated on record drawings.